Month: August 2026

MIE Completes 100kVA UPS Installation and Commissioning at Oferekpe Agbaja Primary Health Centre, Ebonyi State

Master Integrity Energy (MIE) has successfully completed the installation and commissioning of a 100kVA Innovasis Masterline UPS system at Oferekpe Agbaja Primary Health Centre and Diagnostic Centre in Ebonyi State, Nigeria. The project was delivered to support the facility’s MRI diagnostic operations, providing a reliable backup power solution for critical medical equipment. Project Overview Modern …

Reliable Power for Critical Healthcare: MIE Completes 100kVA UPS Installation at Harmony Advance Diagnostic Center, Ilorin

Master Integrity Energy (MIE) has successfully completed the installation of a 100kVA Innovasis Masterline UPS system for Biostadt Ltd at Harmony Advance Diagnostic Center, Ilorin, Nigeria. The project was undertaken to provide a reliable and uninterrupted power solution for the facility’s MRI machine, where stable power is essential for critical diagnostic operations. Project Overview Healthcare …